With only a month to go until our opening day, we have A LOT to update everyone on!

Our construction crews at the Summit are busy working on the final stages of our Summit Lodge. Dry walling and painting are done. Floors are in. Kitchen equipment is installed and being tested. Washrooms are almost done. All our water and sprinkler systems are just getting final touches. In short, we are getting very close!

Painting Summit Lodge

Putting on the first coat of paint
Installing floorboards in the Summit Lodge

Installing the laminate floor
Pipe Fitter at work - Summit Lodge

One of the pipe fitters at work

With the beautiful spring weather that we’ve had for the past few weeks we were finally able to re-open the backcountry access road. Most of the kitchen equipment had to be transported to the top by truck. The snow hopefully will be going pretty quickly now and we can start the final work on the Summit landscaping as well.

Summit Teahouse

Installing the hood fan for the Summit Tea House

We have also finished installing the new aluminum/glass railings for the Summit Lodge Viewing Deck. It has really finished the look for the whole building and by going to the aluminum/glass panels, it leaves the views pretty much uninterrupted.

Summit Viewing Deck

New railings on the Summit Lodge Viewing Deck

The Summit weather station has been assembled and is installed on top of the Summit Lodge. Our Summit webcam has also been installed, and will be visible to the public via our website soon!

Summit Weather Station

The Summit Weather Station being installed

At Basecamp, we have finished grading the lot and have started pouring concrete. Landscaping services surrounding our Basecamp Café & retail shop have started, and we have constructed the children’s play area structure!

Basecamp - Sea to Sky Gondola

Before
Basecamp - Sea to Sky Gondola

After
Children Play Area - Sea to Sky Gondola

Children’s play area under construction

All of our directional and interpretive signs are currently being built by Century Signs, and are being installed as they arrive on-site. We have also moved some of our team to the Basecamp offices, and hope to have our Guest Services desk open to the public April 22nd to start processing passes! Stay tuned to our Facebook page and website for more details on that as we move forward.

Base Station Sign

One of the first signs to arrive

It is a very exciting time for the team and we look forward to sharing the Sea to Sky Gondola experience with you soon!

We value your privacy
We use cookies to enhance your browsing experience, serve personalized ads or content, and analyze our traffic. By clicking "Allow Cookies", you consent to our use of cookies. For additional details view our Privacy Policy.
Cookie preferences

You can control how your data is used on our website. Learn more below about the cookies we use by reviewing our Privacy Policy.

Your cookie preferences have been saved.